Family Leisure Centre (FLC) Expansion Project & Methanex Bowl (MB) Upgrade


 
Project Overview

The FLC expansion has two phases
1)  Upgrading the existing Methanex Bowl sports field.
2)  Expanding the existing FLC facility. 


Click here to view on Youtube.
Designs
We'd like to hear what you think!

FLC Expansion Map May2013  Location Map
Click map to view in full.

 

Project Time Frame

DATE   DESCRIPTION   status

  Phase 1 (Methanex Bowl)    
March - April 2013   Procurement of design consultant (RFP) for MB.   Complete
April - July 2013   Design of MB, including user group consultations.   Complete
May - August 2013   Procurement of construction contractors for MB.   Complete
July - September 2013  

Construction of synthetic turf field successfully completed. 

Official kick-off held September 20, 2013.  Details included in the Press Release.

  Complete
September - December 2013  

Project placed on hold; direction sought from Council to resolve scope/budget misalignment

  Resumed
April 2014   Final field deficiency corrections. View the Methanex Bowl page.   Complete
April - August 2014   Final design and procurement of bleachers; new press box design.   Complete
April 2015    Bleacher / press box construction.     

  Phase 1 complete.    
         

  Phase 2 (Family Leisure Centre Expansion)    
March - May 2013   Procurement of design consultant for FLC.   Complete
July - August 2013   Procurement of Construction Manager.   Complete
May - September 2013   Schematic design of FLC; cost estimates updated.   Complete
September - December 2013   Project placed on hold; direction sought from Council to resolve scope/budget misalignment.   Resumed
December 2013
  Council approves project scope change to remove ice arena component and replace with gymnasium space.   Complete
January  - March 2014    Schematic Design work recommences; includes user group consultations and public information session (March 19, 2014).   Complete
March - September 2014   Detailed Design work and construction drawings.   In progress
August 2014 - June 2016   Construction of new expanded spaces (Field House, Gym, Indoor Track, Fitness)   In progress
Feb 12, 2015   Riverboat Cafe closes   Complete 
March 2015 - August 2015   Renovations to Pool Seating, Front Entrance, Administration area.  
    Phase 2 complete by April 2016    
     

For more information, please e-mail linmac@medicinehat.ca.